Access passes
You do not require special access passes during the setting-up and dismantling times.
Date of delivery for technical order forms
Date of delivery for technical order forms: 02.12.2024
In case of delay, Messe Düsseldorf cannot guarantee handling in due form, and time and/or the services may not be executable anymore.
In addition, any orders and changes or modifications received within 21 days of the commencement of build-up will be subject to a 35% surcharge. The same applies for services utilised but not ordered in advance. Services already rendered must be paid in full.
Construction/Dismantling dates:
Please note the separate information under "Traffic regulations" for vehicles during construction and dismantling time.
Construction:
hall 9 - 11: |
4th January, 7.30 am |
until |
6th January, 6 pm |
In this time the construction is possible day and night (24h). On 6th January, only decoration work may be carried out until 21.00 hrs.
Dismantling:
hall 9 - 11: |
9th January, 5 pm |
until |
10th January, 6 pm |
In this time the construction is possible day and night (24h).
Advanced installation:
An advanced installation will be possible from the 2nd January in all halls.
For the advanced installation it is necessary to make a written application. The application must be submitted no later than 21 days before the desired date construction. Please send it to the following E-Mail or Fax-number:
e-mail: TR-Service@messe-duesseldorf.de
fax number: +49 211 45 60 -85 66
For using the advanced installation a fee of € 495,00 + VAT for each stand per day and additional a security guard has to be paid.
A 35% supplement will be charged for advanced set-up applications received less than 21 days before build-up time.
Please notice, that this is only significant at the time, when all final technical orders and plans for clearance of special structures were received, latest until the respective deadline.