Access passes
You do not require special access passes during the setting-up and dismantling times.
Date of delivery for technical order forms
Deadline for submission of orders for technical services: 08.10.2024
In case of delay, Messe Düsseldorf cannot guarantee handling in due form, and time and/or the services may not be executable anymore.
In addition, any orders and changes or modifications received within 21 days of the commencement before build-up will be subject to a 35% surcharge. The same applies for services utilised but not ordered in advance. Services already rendered must be paid in full.
CONSTRUCTION/DISMANTLING DATES
Please note the separate information under "Traffic regulations" for vehicles during construction and dismantling time.
Construction
halls 8a + 8b: |
5th November, 7.30 am |
until |
10th November, 10 pm |
In this time the construction is possible day and night (24h). After 10 pm on the last construction day only application of decoration is permitted till the beginning of the event.
Dismantling
halls 8a + 8b: |
14th November, 6 pm |
until |
18th November, 4 pm |
In this time the construction is possible day and night (24h).
Advanced installation
An advanced installation will be possible in both halls from the 4th November in booth halls.
For the advanced installation it is necessary to make a written application. The application must be submitted no later than 21 days before the desired date construction. Please send it to the following E-Mail or Fax-number:
e-mail: TR-Service@messe-duesseldorf.de
fax number: +49 211 45 60 -85 66
For using the advanced installation a fee of € 495,00 + VAT for each stand per day and additional a security guard has to be paid.
A 35% supplement will be charged for advanced set-up applications received less than 21 days before build-up time.
Please notice, that this is only significant at the time, when all final technical orders and plans for clearance of special structures were received, latest until the respective deadline.